(3) What is the total expenditure on sponsorship by the ACTPLA, or its predecessors, during the (a) 2001-02, (b) 2002-03, (c) 2003-04 and (d) 2004-05 financial years.

Mr Corbell: The answer to the member’s question is as follows:

(1) $181.00

(2)

2001-02

2002-03

2003-04

2004-05

nil

$1,403

nil

$588

(3)

2001-02

2002-03

2003-04

2004-05

$15,450

$14,000

$13,000

$12,454

Civic Youth Centre
(Question No 546)

Mr Seselja asked the Minister for Planning, upon notice, on 25 August 2005:

(1) What was delivered for the $246 000 of capital expenditure, as at the end of the 2004-05 March Quarter, on the Civic Youth Centre;

(2) Was there any further expenditure on this project in the last quarter of 2004-05; if so, how much and what was delivered for that expenditure; if not, why not;

(3) What is the (a) current total expenditure on this project and (b) completion date for this project;

(4) Is the project running according to schedule to meet that completion date;

(5) Will this project be delivered within its $645 000 budget.

Ms Gallagher: The answer to the member’s question is as follows:

(1) Capital expenditure of $246,000 for the end of the 2004-05 March Quarter was for preliminary work including design fees. This included work for “The Junction” (Youth Health Centre), which is managed by ACT Health and was incorporated into the project.

(2) The expenditure for the last quarter of 2004-05 was $827,000.

(3) (a) The total expenditure to the end of June was $1,073,000.

(b) The construction of the project was completed on the 8 August 2005.

(4) The project was completed on schedule.

(5) Yes.