Hospital Redevelopment Project

QUESTION NO 238

MR BERRY - Asked the Minister for Health, Education and the Arts on notice on 16 August 1990:

1. The 18 July 1990 Hospitals Redevelopment Update outlines

a 7 stage planning process; what stage are we at now.

2. When will we reach stage 3 so that we can know the time scales for the development of capital and operating cost estimates.

MR HUMPHRIES - The answer to Mr Berrys question is as follows:

The stages of Facility planning outlined in the 18 July 1990 Hospitals Redevelopment Update provides an overall framework which is followed in New South Wales and allows people to understand the various processes involved in hospital redevelopment. While presented conceptually as a linear process, in practice these stages often occur in parallel particularly where the planning aspects of some components are more clearly established.

At this time the overall project is still at Stage 1 while some elements are proceeding to Stage 2. The Master Development Control Plan which represents the end of Stage 2, is not expected to be finalised until around March/April next year.