MINISTER FOR URBAN SERVICES

LEGISLATIVE ASSEMBLY QUESTION

QUESTION NO 82

Roadworks - Drakeford Drive

Mr Wood - asked the Minister for Urban Services

In relation to Drakeford Drive, Kambah, when will the long overdue repairs be done to the road?

Mr De Domenico - the answer to the member's question is as follows:

The contractor responsible for the rectification of the sealing works on Drakeford Drive, Pioneer Road Services, is required to undertake the work as soon as the weather conditions permit. Given the recent variation in temperatures and the need to ensure that the rectification works are successful, the work is likely to commence during the warm to hot weather at the end of December 1995 or early January 1996.