Legislative Assembly for the ACT: 2008 Week 10 Hansard (Thursday, 28 August 2008) . . Page.. 4037 ..
Bonython West Infrastructure Duplication of Athllon Drive |
Jun-08 |
Dec-08 |
Government Offices Air Conditioning Upgrade |
Jun-08 |
Oct-08 |
Acton Temporary Car Park |
Jun-08 |
Aug-08 |
Fyshwick Stormwater Augmentation |
Jun-09 |
Jun-09 |
Airport Roads Stage 1 |
Jun-09 |
Dec-08 |
Tharwa Bridge |
Jun-08 |
Dec-11 |
• The delay in acquittal of funding for the projects in the 2007-08 year was unanticipated at the time of original budget forecasts for the 2007-08 year primarily as a result of tight market conditions; particularly those associated with the landscape design and construction industry, as well as higher than anticipated project costs and delays in the supply chain.
• The following table shows the rollover for each project as a percentage of total budget.
Project Name |
Project Authorisation $’000 |
Rollover $’000 |
% of Total Project Budget |
Capital Improvements – Improving the Look of the City |
9,700 |
6,331 |
65% |
Lake Ginninderra Foreshore Upgrade – Stage 2 |
3,200 |
2,675 |
84% |
Lanyon Drive Upgrade (Monaro Highway to Sheppard St) |
5,000 |
1,852 |
37% |
Bonython West Infrastructure Duplication of Athllon Drive |
3,900 |
2,450 |
63% |
Government Offices Air Conditioning Upgrade |
1,410 |
1,350 |
96% |
Acton Temporary Car Park |
2,500 |
1,000 |
40% |
Fyshwick Stormwater Augmentation |
3,800 |
1,000 |
26% |
Airport Roads Stage 1 |
15,000 |
2,000 |
13% |
Tharwa Bridge |
10,000 |
8,400 |
84% |
Construction Industry Long Service Leave Board
(Question No 2216)
Mr Mulcahy asked the Minister for Industrial Relations, upon notice, on 27 August 2008:
• Have any members of the Construction Industry Long Service Leave Board resigned within the last year; if so, for each resignation, (a) what was the reason given, (b) is the Minister satisfied that the reason given was genuine; if not, or if no reason was given, is he able to provide a reason for the resignation and (c) did any resigning Board members criticise the operation of the Board to the Government; if so, what were these criticisms;
• How was the new Chair of the Board appointed;
• Is the Minister satisfied that the Chair of the Board is sufficiently independent from outside groups to perform his functions properly.
Mr Barr: The answer to the member’s question is as follows: