Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Sittings . . . . PDF . . . .
Legislative Assembly for the ACT: 2005 Week 11 Hansard (Thursday, 22 September 2005) . . Page.. 3618 ..
10
Clause 113 (2)
Page 76, line 11—
omit
Schedule 3
Tree Protection Bill 2005
Amendments moved by the Minister for the Environment
23
Proposed new clause 62 (3) (e)
Page 39, line 16—
insert
• each representative Aboriginal organisation.
24
Clause 62 (4)
Page 39, line 17—
omit
25
Clause 65 (3), definition of interested person, proposed new paragraph (f)
Page 42, line 2—
insert
• if the tree is an Aboriginal heritage tree—each representative Aboriginal organisation.
26
Clause 79, note 1
Page 50, line 10—
omit note 1, substitute
Note 1 Conservator to be given copy of development application
The planning and land authority must give the conservator a copy of each development application that relates to land that includes the protection zone for a protected tree or a declared site (including any tree management plan, proposed tree management plan, or proposed amendment of a tree management plan, included with the application) (see Land Act, s 229).
27
Clause 79, note 4
Page 50, line 23—
omit note 4, substitute
Note 4 Approvals
A development approval must not be given that is inconsistent with the advice of the conservator in relation to a registered tree.
A development approval may be given that is inconsistent with the advice of
Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Sittings . . . . PDF . . . .