(2) What is the total (a) size, (b) capacity and (c) construction time of each facility listed in part (1).

Mr Rattenbury: The answer to the member's question is as follows:

(1) a) $300k

b) $350k

c) $350k

(2) a) Calwell 2350sq/m, Mawson 6900sq/m, Gungahlin 11,000 sq/m,

b) Calwell 60 Spaces, Mawson 180 Spaces, Gungahlin 340 spaces.

c) Calwell 5 months, Mawson 8 months total (two separate stages, one in 2010 and expansion in 2013), Gungahlin 3 months (gravel surface).

Questions without notice taken on notice

Government—polling

Ms Gallagher (in reply to supplementary questions by Mr Coe on Thursday, 25 September 2014): ACT Government directorates have not recently authorised or engaged 'The Greasy Poll' to determine support for various infrastructure projects. Directorates are not currently undertaking any telephone polling in relation to the support of various government policies.

It is appropriate to undertake surveying to determine community perceptions and satisfaction with Government policies and programs. This research is often necessary to measure performance as required by annual report outputs reporting and budget processes.

The total cost of these telephone surveys from September 2013 to September 2014 was $519,576.


Next page . . Previous page. . . . Speeches . . . . Contents . . . . Sittings . . . . Search


If you have special accessibility requirements in accessing information on this website,
please contact the Assembly on (02) 6205 0439 or send an email toOLA@parliament.act.gov.au
Accessibility | Copyright and Disclaimer Notice | Privacy Policy
© Legislative Assembly for the ACT