What was the total expenditure every month from July 2005 to June 2010 inclusive, for (a) recurrent and (b) capital expenditure for each department and agency in the Minister's portfolio.

Ms Gallagher: The answer to the member's question is as follows:

(a) In relation to recurrent expenditure, details of each department and agency's YTD expenditure by quarter is published as an Appendix in the Territory Consolidated Quarterly Financial Management Reports, which are available on the Treasury Website at: www.treasury.act.gov.au/about/publications.shtml

(b) In relation to capital expenditure, details of each agency's capital works program expenditure, in total and by project, is provided on a quarterly basis through the capital works quarterly progress reports. These Reports have been provided to Mr Smyth by FOI since March 2006, before that time these Reports were tabled in the Assembly. Since June 2009, these reports have been published by Treasury.

Treasury has, however, now made all these reports available on the Treasury Website at www.treasury.act.gov.au/about/publications.shtml

Finance—departmental expenditure

(Question No 1024)

Mr Seselja asked the Treasurer, upon notice, on 1 July 2010:

What was the total expenditure every month from July 2005 to June 2010 inclusive, for (a) recurrent and (b) capital expenditure for each department and agency in the Minister's portfolio.

Ms Gallagher: The answer to the member's question is as follows:

(a) In relation to recurrent expenditure, details of each department and agency's YTD expenditure by quarter is published as an Appendix in the Territory Consolidated Quarterly Financial Management Reports, which are available on the Treasury Website at: www.treasury.act.gov.au/about/publications.shtml

(b) In relation to capital expenditure, details of each agency's capital works program expenditure, in total and by project, is provided on a quarterly basis through the capital works quarterly progress reports. These Reports have been provided to Mr Smyth by FOI since March 2006, before that time these Reports were tabled in the Assembly. Since June 2009, these reports have been published by Treasury.

Treasury has, however, now made all these reports available on the Treasury Website at www.treasury.act.gov.au/about/publications.shtml

Finance—departmental expenditure

(Question No 1025)

Mr Seselja asked the Minister for Health, upon notice, on 1 July 2010:


Next page . . Previous page. . . . Speeches . . . . Contents . . . . Sittings . . . . Search


If you have special accessibility requirements in accessing information on this website,
please contact the Assembly on (02) 6205 0439 or send an email toOLA@parliament.act.gov.au
Accessibility | Copyright and Disclaimer Notice | Privacy Policy
© Legislative Assembly for the ACT